Renewable Energy - Research & Development
Increasing the Lateral Load Capacity of Monopile Foundations for Offshore Windfarms
Introduction
The cost of offshore wind energy is still greater than that of more conventional
sources electricity, one of the main reasons for this is the high capital
cost of installing the turbines in an offshore environment. A significant
proportion of that cost is the turbine foundation, therefore any reduction
in foundation cost could have a considerable effect on the overall cost.
Currently the preferred foundation option is the monopile. Environmental
forces such as wind and waves exert large lateral loads upon the foundations,
because of these forces monopiles are often significantly longer than
required for vertical load capacity. The aim of this programme is to demonstrate
that the addition of fins to the top of a monopile will result in an increase
in lateral capacity and will allow a reduction in pile length.
The cost of the monopile foundations is governed by steel weight and
the addition of fins may allow the pile length to be substantially reduced
meaning a considerable cost saving. Also the reduced pile length may mean
savings in the piling operations, as the required driving depth has decreased.
Development Programme
SEtech have been working jointly with Newcastle University conducting
a phased development programme into improving the lateral capacity of
monopile foundations. The initial investigations are concentrating on
the monatomic loading of piles.
Phase One
The aim of Phase 1 was to use computer modeling to show that the addition
of fins to a monopile would give an increase in lateral capacity. Software
designed for the analysing laterally loaded piles was used and the fins
were modeled as an increase in pile volume and stiffness. The results
of the modeling showed that the fins had a noticeable effect in increasing
the lateral capacity of the piles.
Phase Two
Following the success of the computer modeling, Phase 2 commenced in March
2003 and constituted the small-scale model testing of finned piles. The
testing was carried out in the Soil Mechanics Laboratory at Newcastle
University using 1/100th scale models with various fin configurations.
During the tests an increasing load was applied to the piles and the resulting
displacement was measured as well as the load. Plotting the results show
the piles fins give an increase in lateral capacity that the size of the
fin has a significant effect.
Phase Three
The aim of Phase 3 is the installation and testing of large-scale model
piles in the artificial seabed at the Euro-Seas Engineering Solutions
& Testing (EEST) facility in Blyth, Northumberland. The 8 piles are
approximately 1/16th scale. The lateral load testing of the piles will
shortly be underway and the initial results will be available soon. |